October 2026: Engineering Assessment Underway

October 15 Site Assessment
SME conducted on-site engineering assessment work at the Vinsetta Bridges on October 15, 2026, marking an important step toward planning for their preservation. The City-funded assessment covers the four historic bridges at Mayfield, Greenleaf, Woodsboro and Cedar Hill, following the Royal Oak City Commission's unanimous funding approval on August 10.

The site work included drilling and collecting concrete core samples from three bridges. These samples, together with field observations, will help engineers evaluate the concrete's condition and develop recommendations for future work. The assessment will provide a stronger basis for decisions about preserving these century-old landmarks.

What Happens Next
The next stage brings together laboratory analysis and engineering review. The assessment is intended to provide findings, preliminary repair recommendations and estimated costs to guide preservation planning and future funding decisions. Funding for the assessment is in place; restoration work will require further decisions and resources. A final report date has not yet been confirmed. 

Contact the VBTF

© Copyright 2026 Vinsetta Bridges Task Force
Royal Oak Historic District Commission
Royal Oak Historic District Study Committee